Northern Force Dance Studio
Blaine, MN
- Office
- Manufacturing
- Warehouse
- Retail
- Specialty: Dance Studio
Project Highlights
- Within budget
- On schedule
- Temporary wall and phased scheduling used to allow lessons to continue during construction
- 9.8k Total Square Feet: 7.4k First Floor | 2.4k Second Floor
Recognized as one of the top dance schools in Minnesota and the nation, Northern Force needed additional dance studio space, more storage, and expanded administrative capacity to support continued growth.
The studio required more training space and second‑floor storage while maintaining uninterrupted dance programming. They also needed updates to their aging facility, including improved lobby space, a full roof replacement, and new HVAC systems, all without disrupting daily instruction.
- Shaw collaborated with the owner to align design, budget, and performance requirements
- Met with the City of Blaine and the Watershed District to ensure compliance
- Structural design addressed snow loads on both existing and new construction
- Addition intentionally designed to avoid the cost of an elevator
Construction began in October 2015 and was carefully scheduled around active dance lessons. Shaw built a temporary enclosure to protect the existing studio after removing a shared wall, enabling classes to continue without interruption. Work was sequenced to avoid winter‑condition costs, and specialized measures—including recessed concrete floors—were implemented to support the unique performance flooring required for dancer safety.
Northern Force Dance Studio received a seamless addition that expanded training capacity, increased storage, and upgraded the overall facility. The project was completed without interrupting lessons, enhanced client experience through an expanded lobby, and improved building performance with new roofing and HVAC systems.
Solutions Required
Dance studios require unique, shock‑absorbing flooring to prevent injuries.
Shaw recessed the concrete slab to allow installation of specialized flooring without creating raised thresholds.
Renovations included expanded lobby, new roof, and complete HVAC replacement
A temporary enclosure replaced the removed wall, and construction activities were scheduled when classes were not in session.