Skip links

States Manufacturing

Shaw continues to exceed our expectations. They delivered our project on an accelerated timeline and we couldn't be happier with their work. We continue to leverage Shaw for our future expansion needs in the greater MSP area.
Jason Forcier | CCO

States Manufacturing

Dayton, MN

Project Highlights

States Manufacturing, a long‑term design/build partner of Shaw, needed a significantly larger and more specialized manufacturing footprint to keep up with rapid production growth. Their new leased space at The Cubes required substantial build‑out to support office expansion, multiple shop areas, heavy equipment loads, and warehouse functionality.

The client needed to be operational within six months, requiring a fast‑tracked build‑out that supported heavy manufacturing equipment, crane operation, and multiple office environments. They required major infrastructure additions—including large drive‑in doors, specialized MEP systems, and production‑ready shop layouts—while ensuring the space could come online in strategic phases to accelerate manufacturing start‑up.

  • Full design/build approach with accelerated budgeting to help the client make informed decisions early
  • Integrated design for crane loads, manufacturing equipment, and clear‑height requirements
  • Coordination of architectural, structural, civil, MEP, voice/data, and low‑voltage systems
  • Demo and reconfiguration of portions of the existing spec office area

Construction was fast‑tracked to meet the client’s six‑month operational deadline. Shaw coordinated all design disciplines early to streamline permitting, identify long‑lead items, and phase construction so critical manufacturing areas could open first. Major work included cutting in new drive‑in doors, installing crane‑supporting structural systems, and upgrading HVAC, lighting, and warehouse finishes—all while sequencing work for phased occupancy and early production start‑up.

States Manufacturing successfully launched operations just five months after construction began, with remaining areas completed while production was already underway. The project delivered fully functional office and manufacturing environments, new access points, integrated equipment support, and comprehensive system upgrades, positioning the company for rapid growth in the Twin Cities market.

Solutions Required

The client needed to be operational within six months.

Shaw identified priority areas, fast‑tracked their build‑out, and worked with inspectors to secure phased occupancy.

Shaw cut in new 30’ x 40’ and 13’‑6” x 16’ openings, installed structural supports, and executed related sitework.

Structural systems were engineered for crane loads, and Shaw coordinated equipment integration and required footings.

Shaw managed architectural, civil, structural, MEP, voice/data, security, low voltage, card access, and AV scopes internally under a unified design‑build delivery.